Transport infrastructure
Construction

Renovation of the Flora Metro Station

Project name:
Complete Renovation of the Flora Metro Station
Location:
Praha 3 – Žižkov
Flora
Vinohradská
Investor:
Prague Public Transit Company, joint-stock company
Typology:
Transport infrastructure
Status:
Construction
Project start:
2026 Q1
Project completion:
2026 Q4
Total investment:
CZK 1.293 billion
Updated:
10/8/2025
Sources:
Dopravní podnik hl. m. Prahy, a. s., dpp.cz

Photos of the station's current condition

Author: Petr Hejna , Source: DPP

Photos of the station's current condition

Author: Petr Hejna , Source: DPP

Photos of the station's current condition

Author: Petr Hejna , Source: DPP

Photos of the station's current condition

Author: Petr Hejna , Source: DPP
01/04

Photos of the station's current condition

Author: Petr Hejna
Source: DPP

In October 2025, Dopravní podnik hl. m. Prahy (the Prague Public Transit Company) handed over the construction site to the winning contractor—a consortium of STRABAG and OHLA ŽS—for the complete renovation of the Flora metro station.

The main scope of the complete renovation will include:

  • replacement of the original escalators, which are more than 45 years old
  • construction of barrier-free access via elevators
  • complete renovation of the concourse and platform
  • renovation of electrical wiring, lighting, ventilation, and other systems
  • renovation of the distribution substation and other operational areas
  • rehabilitation of building structures
  • modernization of fire safety systems.

As part of this extensive investment project valued at 1.293 billion crowns, Flora will become the 49th barrier-free station in the Prague Metro.

Construction work will proceed in phases and will last a total of nearly 29 months. Starting February 2, 2026, Flora station will be closed for approximately ten months, in part to replace the escalators. It is expected to reopen around the end of November or beginning of December 2026. Both DPP (the Prague Public Transit Company) and the contractors anticipate that the elevators in the new barrier-free section will become operational during the first quarter of 2028.